Undervoltage trip on bus-tie opening
A replacement breaker's UVT coil did not match. A first fix failed and pointed to the switching sequence; a 1 s off-delay timer cured it and the drawing was updated.
MCCB Kept Tripping for 1 YearEngineering dossier
Registered Electrical Engineer since 2008. Six years of HV/MV testing and commissioning, then ten years at sea as a marine ETO. Test plans, test reports, work methods and costing, re-typeset from my own work files. In the reports, client staff names and client asset serials are blacked out; prices withheld.

Career timeline
Marine ETO dossier, 2016 to now







The Probing Loop: identify the real mechanism, probe on paper then with a test that can fail, steer by the result, seal with the fix, the record and the updated drawing.
A replacement breaker's UVT coil did not match. A first fix failed and pointed to the switching sequence; a 1 s off-delay timer cured it and the drawing was updated.
MCCB Kept Tripping for 1 YearFound and repaired broken cylinder-2 wiring, then proved the start chain stage by stage on turning gear. That sent the search to the pilot valves; the start test passed.
Main Engine Starting Failure, Part 2Past role, 2009 to 2016
Technical Services Engineer, United Services Corporation, Manila. MV/HV testing and commissioning up to the 34.5 kV class, costing and proposals, crews, reports and close-out.
| Scope | What the record shows |
|---|---|
| HV/MV testing and commissioning | Seven 34.5/6.6 kV, 3 MVA power transformers (Philippine Arena); a 38 kV, 2000 A outdoor vacuum breaker on a 34.5 kV system |
| Protection relay testing | 16 SEPAM relays by secondary injection: phase and earth-fault overcurrent, overvoltage, over- and under-frequency |
| OMICRON and Megger test sets | CPC 100 with CP TD1; Megger 120 kV DC set and OTS60PB oil tester, named on the reports; breaker timing on a CIBANO 500 by our testing subcontractor |
| ITPs and ITRs | An ITP I prepared (2011); a test plan from my approved procedure; signed, serialised reports quoting the acceptance limit |
| Risk assessment and work methods | Lift beneath energised lines: hazards, controls, permits, lockout, lifting plan and a written stop rule |
| SF6 switchgear | ABB SafePlus SF6-insulated ring main unit, 13.8 kV, 630 A (2012): IR, functional and fault-indicator checks, released for energisation |
| Costing and commercial | Bottom-up estimates, signed proposals, proposed versus actual review |








ITP TIPI-ITP-001-11: 13.8 kV plant substations at a semiconductor manufacturer, with USC as testing subcontractor to the main electrical contractor. Sign-off columns for client, USC and others. Tied to work method WMS-001-11: scope, crew of four, test equipment (CPC 100 with CP TD1, Fluke sets) and a HIRARC risk appendix.
| Task | Conformance criteria | Verification record |
|---|---|---|
| Facility and equipment preparation | Verify proper connection | Visual and schematic inspection |
| Calibration of circuit breaker protective relays | Conformance to primary calibrating equipment | Visual and schematic inspection |
| Calibration of over- and undervoltage relays | Conformance to primary calibrating equipment | Visual and schematic inspection |
| Contact resistance on circuit breakers (normal and emergency) | Manufacturer's published data | Visual and schematic inspection |
| Transformer winding insulation integrity | Manufacturer's published data | Left blank on the original |
| Transformer turns ratio | Manufacturer's published data | Left blank on the original |
| Transformer IR with polarisation index | Manufacturer's published data | Left blank on the original |
| Lightning arrester insulation power factor | Manufacturer's published data | Left blank on the original |
| Activity | Method | Acceptance |
|---|---|---|
| Visual and mechanical | Nameplate against drawings and specification; torque checks; earthing; accessories | Checklist complete |
| IR and polarisation index | 1 and 10 min, HV-LV, HV-earth, LV-earth; corrected to 20 °C | NETA ATS Table 100.5; PI > 1.0 |
| Turns ratio, every tap | Three-phase equivalent per tap, against nameplate | Error ≤ 0.5% |
| Winding resistance, every tap | DC per phase, both windings; temperature recorded | Within 5% of factory or sister unit |
| Power factor and capacitance | Tap at neutral; temperature-corrected | 0.5% HV-LV, 1.0% to earth |
| Excitation current | Same voltage each phase, against factory and sister units | Two outer phases similar, middle lower |
| Oil dielectric breakdown | 2.5 mm gap, 3 min settling, 3 kV/s, five fillings | Not below 30 kV |
Transformer Testing and Commissioning Procedures, Rev.1, Sept 2013. Prepared by L.Q. Regio. Scope: 7 × 34.5/6.6 kV and 11 × 6.6/0.38 kV units.
| Insulation resistance | 1 min | 10 min | PI |
|---|---|---|---|
| HV-LV, 5 kV | 15.2 GΩ | 113 GΩ | 7.43 |
| HV-earth, 5 kV | 5.39 GΩ | 10.0 GΩ | 1.85 |
| LV-earth, 2.5 kV | 6.00 GΩ | 14.9 GΩ | 2.48 |
| Power factor | C (nF) | PF @ 20 °C |
|---|---|---|
| HV-LV, 5 kV | 2.651 | 0.23% |
| HV-earth, 5 kV | 1.330 | 0.57% |
| LV-earth, 2.5 kV | 3.819 | 0.47% |
Excitation at 5 kV: 11.16 / 4.14 / 11.05 mA (A / B / C). Oil breakdown: five fillings, 27.0 to 42.3 kV, average 35.5 kV; one filling below the report's 30 kV line. All instruments serialised. 3 MVA, 34.5/6.6 kV, Dyn11. USC-TR-001-13, 11 Dec 2013. Tested by L.Q. Regio and a co-tester.
| Feeder 01, SEPAM 40 | 150% I (A) | t (s) | 150% Ie (A) | t (s) | 300% I (A) | t (s) | Inst. I (A) | t (s) |
|---|---|---|---|---|---|---|---|---|
| Phase A | 4.8 | 7.826 | 1.425 | 3.652 | 9.6 | 1.887 | 60 | 0.240 |
| Phase B | 4.8 | 7.842 | 1.425 | 3.724 | 9.6 | 1.862 | 60 | 0.232 |
| Phase C | 4.8 | 7.816 | 1.425 | 3.760 | 9.6 | 1.926 | 60 | 0.264 |
| Generator 01, SEPAM G87 | Injected | Trip time (s) |
|---|---|---|
| Overvoltage, A / B / C | 140 V | 1.005 / 1.005 / 0.993 |
| Overfrequency | 62 Hz | 1.255 |
| Underfrequency | 59 Hz | 1.252 |
7.73 to 7.90 s trip band at 150% and 1.83 to 1.93 s at 300% across all 16 relays (8 × SEPAM 40 feeder, 8 × SEPAM G87 generator). HVX vacuum breaker, Feeder 01: IR at 2.5 kV 151 to 421 GΩ (limit 2 GΩ); contact resistance at 400 A 32.60 to 33.23 µΩ, spread 1.9%; one sheet per breaker, 16 breakers. Relay Functional Test Report, Philippine Arena, 25 to 27 March 2014. Tested by L.Q. Regio. I test relays against the settings issued for the job; I have not calculated settings.
Page 1 of each signed report. Client asset serials and other people's names blacked out.






| Site | Scope |
|---|---|
| ICTSI Berths 5 and 6 (Cummins) | PIX12 7.2 kV switchgear, HVX breakers, SEPAM relays; 3 MVA transformer, NER, 4 × 2.28 MVA 4.16 kV gensets |
| Texas Instruments, Baguio | Eight 13.8 kV substations tested in 2011, as testing subcontractor to the main electrical contractor |
| Balesin Island (Alphaland) | 13.8 kV island network: 13 ABB distribution transformers; ABB SafePlus SF6-insulated ring main unit, 630 A (2012) |
| MATES and Tong Hsing | 34.5 kV class transformers: ratio, winding resistance, PF, oil DBV, IR scans |
| Breaker test, 38 kV vacuum breaker | Result |
|---|---|
| IR at 5 kV, closed and open | 27.9 to 165 GΩ, balanced across phases |
| DC withstand, 70 kV, 60 s | 14.1 / 17.9 / 17.7 µA, held |
| Contact resistance at 100 A | 47.23 / 46.55 / 47.55 µΩ (OEM as-new limit 52 µΩ) |
| Timing: open / close, O-C-O sequence | 43.7 to 43.8 ms / 55.5 to 56.1 ms; pole spread 0.1 ms opening, 0.6 ms closing |
| Minimum pick-up, ramp to 125 V | Trip coil 35 V, close coil 60 V |
Timing and pick-up were run by our testing subcontractor on an OMICRON CIBANO 500 and carried into our signed report. IR, withstand and contact resistance are our own tests (CPC 100, Megger 120 kV DC, Fluke 1550B). 38 kV, 2000 A outdoor dead-tank breaker. Test report USC-TR-001-15, 21 to 22 May 2015, witnessed by the client. Tested by L.Q. Regio and a co-tester.




“For any hazard or irregularities being observed, stop and notify the supervisor, leadman and safety officer to check and resolve prior to go on.”Stop rule, in the method
No one under a suspended load. Safety officer on site for the whole lift. Arc flash from approach to live lines listed and controlled. Positioning and installation procedure using A-frame, 6 May 2015. Prepared by L.Q. Regio, approved by the General Manager.
| Cost head | How it is built |
|---|---|
| Proposal summary | One pay item per equipment and test package |
| Unit price analysis | Labour = headcount × rate × hours; overtime factor 1.25 |
| Equipment | Test-set charge from cost recovery over utilisation |
| Materials and logistics | Consumables, transport, fuel and tolls, accommodation, permits |
| Overhead, contingency, profit | Markup versus margin, applied deliberately |
Bids and proposals I prepared include 115 kV and 69 kV substation T&C bids, a substation T&C estimate, the Lafarge Teresa proposal (Rev 1, with deductive and additive items), and the Philippine Arena switchgear and transformer proposals. Client prices withheld.
| Where the price went | Share of direct cost |
|---|---|
| Delivery and lift | 53% |
| Testing and commissioning | 36% |
| Preliminaries | 11% |
| Line | Actual vs proposal |
|---|---|
| In-land transport | −14.0% |
| Customs clearing (not needed) | −100% |
| Total direct cost | +5.8% |
| Overhead and profit | −19.9% |
Transformer package, Philippine Arena: 30 working days, 240 regular plus 76 overtime hours. On a heavy-equipment job the lift, not the testing, carries most of the cost and the risk. I priced testing from crew-hours I knew. Peso values withheld.
Beyond the test set
Methods, test plans, reports and handovers that others can follow. Excel estimating; Word and PowerPoint.
I write, film and edit short technical videos on real fault-finding for junior electro-technical officers. It keeps my explanations clear for clients and new technicians.
Supervised crews of engineers, foremen and technicians; wrote the department's job descriptions and technical tests; ran in-house training on transformer maintenance and testing.
One written brief per AI agent; independent views from different models, then one synthesis; a model from a different vendor checks the work before I see it. AI drafts; I verify every number against the source and sign. Client data stays in approved tools.
Education and recognition
| Year | Award or qualification |
|---|---|
| 2008 | Registered Electrical Engineer, Professional Regulation Commission |
| 2008 | Team Champion, 5th IIEE national Philippine Electrical Code quiz show |
| 2008 | Special Award in Science and Technology, Technological University of the Philippines |
| 2008 | B.S. Electrical Engineering, Technological University of the Philippines |
| 2002 to 2005 | DOST-SEI science and technology scholar; Diploma in Electrical Engineering Technology |
| 2002 | High school class valedictorian; Philippine Senate Gold Medal for Academic Excellence; Eagle Scout |
Originals of every record on this page are available on request through the contact links on probelem.com.